Matra Petroleum mobilises rig for well-12
StockMarketWire.com
Matra Petroleum says that a rig has been contracted to undertake side-tracking operations on well-12 and mobilisation to the site has begun.
Remedial cementing operations have now been completed on well-13. After a short flow period to ascertain if the water has been successfully isolated, the well will be shut-in while surface production equipment is installed before restarting production.
MD Peter Hind adds: "The remedial cementing on well-13 appears to have gone well. We will know if we have successfully isolated the water zone once production is started.
"We are pleased to be starting work on the well -12 side-track which will be supervised by Fosco, a highly experienced Russian contractor."
Operational Update
http://moneyam.uk-wire.com/cgi-bin/articles/201012140700068658X.html