New pics just in.
Grain Leg - 12.12.06 ...........................Hammer Mills - 12.12.06 ................... View of Plant - 12.12.06


During November 2006
* Delivered Lab Equipment & Overhead Doors
* Ongoing ICM training of IRE plant operations personnel
* Continued installing large bore ductwork in the Energy Center
* Completed Installation of the ID fan, thermal oxidizer and ductwork
* Continued installing insulation on plant piping, vessels and equipment
* Continued installation of the foundations for the grain conveyor/DDG tube. Completed installation of the steel supports and racking for the conveyor
* Completed installation of the DDG feed tube from the Process Building to the grain solos
* Completed installation of the hammer mills and scalpers in the Grain Silo
* Completed installation of cable tray, wiring and terminations in the Grain Silo MCC Room. Completed portions are being energized.
* Completed Process Building instrumentation and pipe installation
* Continued pulling and terminating cable in the Process Building
* Completed installation of Process Building and Energy Center siding
* Completed Process Building and Energy Center roof & insulation
* Continued painting of plant system piping
* Commenced heat trace installation on system piping
* Completed installation of Pumphouse MCC Equipment. Completed portions are being energized
* .Complete DSC Installation
* Continued installation of plant fire protection piping
* Completed Pump House Structure. Completed tank erection.
* Commenced painting of inside of water tank
* Energized permanent power to site switch cabinets and transformers. Equipment has been locked out to provide only authorized access.
* Hydrotesting of Tank farm tanks has commenced.
* Completed erecting Tank Farm pipe rack and installing piping
* Completed last portion of the rail track servicing the Receiving Building
* Completed installation and certification of the truck scales
* Completed grading, shaping and asphalt paving of site roadways
* Commenced bumping of Process Building & Energy Center motors
* Start Up of Grains has commenced
* Corn shipments commenced 16th November and Silos are being filled.