The plant is coming along very nicely all on time for a Q4 start up I have been topping through out the year, after start up I dont think we will be seeing these prices.
During July 2006
* Delivery of major equipment; boiler, beer column, CO2 scrubber
* Installed CO2 scrubber next to Beerwell
* Completed the NW Fermentation Tank & Commenced erection of the NE Fermentation Tank
* Completed pour of Grain Silo roof
* Continued Process Building equipment and pipe installation
* Continued masonry wall construction in the Process Bldg. & Energy Center
* Completed the Cooling Tower pipe rack erection
* Continued Cooling Tower supply and return piping installation
* Delivered and set the boiler in the Energy Center
* Continued site water and fire water installation
* Commenced permanent site power installation
* Installed structural steel, siding and roofing for the Maintenance Building
* Moved into the new Administration Building
* Commenced formwork and pouring for the Receiving Building foundation
* Installed the Tank Farm liner and stone
* Poured Tank Farm foundations and commenced erecting tanks
As of August 2006 the overall work continues to progress on time and
on budget. The project is on course for a quarter four 2006 start up.