Preliminary Results for the seven-month period ended 31 December 2015(Continued)
Operations Report
Dear Shareholder,
I am pleased to report on operational matters at GDC, where focus during the period has progressed from delivery of grid power to planning for expansion. Our operations are both upstream and downstream, so obtaining the optimal expansion strategy requires us to balance reserves and processing capacity against demand for our gas in and around Douala and having the infrastructure in place to reach the market.
During the period, we sold 1,736mmscf of gas (846mmscf for the seven months to 31 December 2014). The average daily rate of gas production for the whole of the reporting period was 8.57mmscf/d (3.95mmscf/d for the seven months to 31 December 2014). Condensate offloaded during the period was 26,055bbls (13,598bbls for the seven months to 31 December 2014).
Thermal Gas Connections and Gas Sales Agreements ("GSAs")
Dangote was commissioned in June 2015. Sic Cacaos and New Foods were both commissioned at the end of May 2015, and June 2015 was their first full month of consumption, and all three of the aforementioned have been consuming consistently ever since. New Foods and Sic Cacaos are consuming at their expected levels and Dangote continues to increase production at its new clinker plant.
Our newly established marketing and sales team is focused on increasing our reach into the Bonaberi area and during the period, eleven new GSAs were signed.
Pricing
GDC has a contract price bracket of $9 to $16/mmbtu for its gas sales and a sales price for its condensate based on the Brent oil price. The fall in the market price of alternate products to our gas has made them more price competitive than previously, resulting in a small number of customers switching to alternative fuels.
We market the benefits of using gas, including uninterrupted supply, time and effort saved on deliveries and logistics, no contamination of final products, cleanliness and environmental benefits and the vast majority of our customers recognise the strength of this argument.
Grid Power
The seasonal nature of our business has been demonstrated since the grid power customer ENEO started consuming gas in line with the wet/dry season and the take-or-pay conditions of their contract.
GDC has maintained continuous and uninterrupted gas supply to both the Bassa and Logbaba power stations and has proved its ability to deliver on supply commitments in accordance with the agreements we have signed.
During the period, the short-term Genset equipment rental contracts with our industrial power customers came to an end as did the related GDC contract with the provider of the Gensets. GDC remains a gas supplier to these customers under GSAs.
Bonaberi Pipeline Extension
Towards the end of 2014, GDC completed Phase I, approximately 2.2km, of the Bonaberi line to its pipeline network after successfully laying pipe and delivering gas under the Wouri River. During this reporting period, our sales team has identified new potential customers and has obtained signed commitments from a number of them to support a subsequent two-phase expansion of the pipeline.
Phase II Bonaberi line extends the existing pipeline from Magzi 2 Industrial Estate to Maya Oil factory, a distance of approximately 8km. The two material customer connections on this phase are Maya & Cie and SMS Shal. The larger of the two is Maya & Cie; a cooking oil and soap producing company located on the Bonaberi Road. Their initial estimated consumption is expected to be 380,000scf/d but we are factoring in a higher pipeline capacity in anticipation of increased demand from Maya.
The delivery of earthworks for this Phase II Bonaberi extension has been outsourced to and coordinated with SOGEA SATOM Succursale Cameroun, the company contracted by the Government of Cameroon to lay bitumen along the Bonaberi road. By contracting their services to carry out the trenching work simultaneously with the construction work on the major road, a significant cost and time saving has been achieved. At the time of approval of the financial statements 3.7km of pipe has been laid and commissioned and an additional 1.3km of pipe has been welded and is ready to be laid. The customers on Phase II Bonaberi are expected to come online during Q3 2016.
Bonaberi is a new and fast growing industrial area in Douala building out to the new Magzi 3 Industrial Estate. Bonaberi is a less densely populated area of Douala than the port side of the Wouri River, which makes the pipe laying and testing less complicated. With ease of access to Bonaberi through the new bitumen road and access to GDC's gas distribution pipeline network we believe using our gas will be significantly more attractive for prospective industrial companies.
Beyond Maya Oil, upon completion of Phase II Bonaberi pipeline, the Phase III Bonaberi pipeline will commence. This is planned to add an additional 5.5km to five new customers with 130,000scf/d of expected consumption. These customers are anticipated to be online in late 2016.
Cost Reduction
Having gone through an initial production and sales growth phase, the Group aims to increase profitability in 2016, both through increased revenues and via operational and corporate cost reductions.
During the period, we have reduced our salary bill and renegotiated a number of supplier contracts, and expect further cost savings to materialise throughout 2016.
Drilling Programme
During the period, GDC has been preparing to drill two wells onshore at the Logbaba Field to supplement the two existing Logbaba production wells. The new wells are required to meet the demand for Logbaba gas, to develop Logbaba reserves and to move some of our 2P (Proven plus Probable) reserves into the 1P (Proven) reserve category. One of the wells will twin the La- 104 well drilled in 1957; the other well will be a 'step-out' well that will be drilled into a target that is intended to add to our Probable reserves. Both of the wells will be drilled directionally from the one drilling pad adjacent to the Logbaba gas plant and they are to be tied into our production facilities immediately after they are drilled and completed. The La-104 twin-well is almost vertical; the 'step-out' well will be drilled to intersect a target that is about 1,100m to the South-East of the Logbaba drilling pad.
Both wells are intended to be production wells from the Logbaba Formation, which is a thick sequence of interbedded sands and shales found at depths between 1,700m and 3,200m below the surface. In addition to developing the gas reserves in the Logbaba Formation, one of the wells, the La-104 twin, has an optional additional objective of an 'exploration tail.' This could be drilled from the base of the Logbaba Formation (approx. 3,200m) down to 4,200m below the surface to test the hydrocarbon potential of the Mundeck Formation which had gas shows in well La-104.
GDC has sourced a drilling rig from Savannah Oil Services Cameroon S.A., an independent private Cameroon company and the rig is currently being shipped to Cameroon. Savannah has supplied a rig in accordance with the specifications determined by GDC subsurface team and SPD Petrofac, taking into consideration high pressure and high temperature drilling conditions. The rig will be mounted on rails between the two well locations, allowing efficient batch drilling to be undertaken using a single unit. SPD Petrofac is providing well design and project management services and with their assistance we are now working on the detailed design and programme preparation.
Major site preparation work is underway including slope stabilisation, leveling for drilling rig tracks and drilling pad preparation. New warehousing for rig supplies, storage and camp civils are also under construction. Long-lead orders have been placed.
During the period GDC carried out a security review on its operations in Douala. A number of the priority items have been implemented in order to be completed in time for the drilling programme such as improved security fencing, CCTV and lighting, improved access controls and new security offices.
The budget for the two-well drilling programme totals less than $40 million, excluding the optional exploration tail, and at the time of approval of the financial statements, GDC is still expected to remain within budget and on schedule.
Logbaba Gas Plant Capacity Expansion
Following the purchase of the gas processing plant in May 2015, Expro International BV has completed the process plant expansion study. Stage one of the gas plant expansion to 25mmscf/d capacity (from 20mmscf/d) is in the preliminary engineering phase. Further expansion phases will tie in with the well results.
Matanda
Negotiations during the period resulted in the announcement of the assignment of a 75% interest in the Matanda Block, adjacent to current Logbaba gas production operations, and the subsequent Cameroon Government approval of the assignment. Matanda covers an area of approximately 1,235km2, over 60 times the area of the GDC Logbaba concession and is highly prospective for significant natural gas and gas condensate resources. The North Matanda Field is estimated to hold an estimated P50 'gas-in-place' volume of 1.8tcf and 'condensate- in-place' of 136mmbbls.
Gaz du Cameroun Matanda S.A., a subsidiary of VOG, and AFEX, a Bahrain based company which has the remaining 25% interest, have submitted a new work programme to the Government of Cameroon for approval and expect to commence the first phase of seismic data acquisition in Q4 2016 after completion of the Logbaba drilling programme. The assignment of the Matanda Block complements the Group's current plan to increase its operating footprint in Cameroon. The existing Logbaba gas network infrastructure will also allow for fast-track development of any new discoveries made on Matanda to deliver additional natural gas to local industrial users in Cameroon.
During the period, the Company undertook an initiative to collate all existing seismic data on the Logbaba Field in order to reprocess it using modern techniques. By coordinating with SNH, the Company succeeded in locating 152km of 2D seismic data from three separate surveys. Post period a reprocessing services tender was run and a successful bidder selected to commence test processing of three 10km segments. With the information attained from this newly reprocessed data, the Company will be able to define the parameters for any additional seismic (2D or 3D) acquisition programme in the urban areas of Logbaba with a much greater level of accuracy, as well as expanding the underlying data-set for future reserves calculations. The addition of new subsurface information will also assist in de-risking future wells beyond the 2016 two-well programme.
All of the achievements of GDC in recent months would not have been possible without the hard work, dedication and loyalty of the team on the ground in Douala and I want to express my sincere gratitude and thanks to each one of them for making GDC a success.
Ahmet Dik
Chief Executive Officer,
Gaz du Cameroun S.A.
29 May 2016
****Further details from link below****
http://www.moneyam.com/action/news/showArticle?id=5350673