CHAIRMAN'S STATEMENT
Dear Shareholder,
On behalf of the Board I am pleased to report our unaudited results for the six months to 30 November 2014 and to update you on company developments beyond the financial period.
During the six months to 30 November 2014, the Group's objectives were to:
· Increase gas production and to make Gaz du Cameroun S.A. ("GDC") operationally cash positive;
· Strengthen our Board and corporate profile;
· Stabilise operations and processes and develop our people within the Group;
· Build strong working relationships with our Logbaba partners RSM Production Corporation ("RSM") and Société Nationale des Hydrocarbures ("SNH");
· Secure major new supply contracts involving power generation for the National Grid in Cameroon.
The management teams of Victoria Oil & Gas Plc ("VOG" or "the Company") and GDC excelled during 2014, meeting all of the above objectives for the reporting period and delivering positive results in the areas of engineering, sales and corporate developments.
Logbaba Gas Project, Cameroon
Following extensive planning and negotiations during the reporting period, GDC signed a legally binding term sheet with ENEO Cameroon S.A. ("ENEO"), Cameroon's integrated utility company, in late December 2014, to supply gas to two power stations, located in the city of Douala. Logbaba and Bassa power stations will generate up to 50MW from Gensets, supplied by Altaaqa Alternative Solutions Projects DWC‑LLC ("Altaaqa"). The agreement includes 'take-or-pay' consumption rates and allows GDC to establish a secure level of gas sales at an attractive price of $9/mmbtu. The power stations' minimum gas consumption will be approximately 9mmscf/d in the January-June dry season and 3mmscf/d in the July‑December wet season. The contract is for two years and extendable by mutual agreement. This project could treble GDC's current gas production. We expect average annual production for the 2015 calendar year to be about 10.4mmscf/d.
In the release of our 2014 Annual Report we quoted our 7 day week July 2014 production of 3.9mmscf/d at GDC. Since then, from August 2014 to January 2015 inclusive, our monthly average daily rate based on a 7 day week has ranged from 3.9 to 4.4mmscf/d. For the same period our monthly average daily rate based on a 5 day working week has ranged from 4.1 to 4.6mmscf/d and the monthly daily peak production rates have ranged from 4.5 to 5.3mmscf/d.
I am proud to report that GDC has substantially completed its scope of work for the ENEO project construction phase and safely built and tested gas pipelines to both stations. We have issued a completion certificate for the Bassa station and expect to complete the Logbaba station within two weeks. The project is scheduled to be online by the end of Q1 2015 and if this is achieved, as we expect, it will represent a remarkable success for the GDC, ENEO and Altaaqa teams. Progressing from signing legally binding terms sheets in late December 2014 to delivering 50MW to the grid approximately three months later is outstanding.
The period was not without its challenges, such as securing the release of gas-fired electricity generations sets ("Gensets") from the local customs and the delay on the Wouri River crossing. However GDC now has access to a wide base of thermal gas customers on the Bonaberi side of the river. GDC is also in the process of making final connections to the Dangote cement plant, a business located on the Douala shore and a major thermal supply customer. Total pipe laid to date in Douala is now 31.3km.
During the period, VOG maintained a good working relationship with Logbaba Field development partners RSM and SNH. Following a settlement agreement between VOG and RSM in January 2014, a cost review process overseen by Akintola Williams Deloitte, Nigeria was undertaken to look at retrospective development expenditure. The review resulted in RSM paying significant development contributions ($10.1 million) and both companies are now working together to unlock the full potential of the Logbaba Field. An additional $6.9 million was received from RSM in February 2015.
One of the most important tasks undertaken during 2014 was the development of our people. At the beginning of the reporting period, we appointed a business-training company, Gallop Solutions International Ltd, to work with us to create an effective workforce with the right skill sets to deliver value for VOG. Our teams within VOG and GDC are now a cohesive, effective team working to build cash flow and a brand synonymous with safe, reliable gas supply.
Post period, in January 2015, the GDC subsurface team successfully conducted a rigless workover of Well La-106. The work utilised specialist coiled tubing, high-pressure pumping and wireline equipment to perform cement remediation work on the well. Initial well flow-tests of Well La-106 were at 5 to 6mmscf/d and the well can provide back-up for Well La-105.
In February 2015, we took the opportunity to utilise the specialist equipment and personnel used on the Well La-106 workover to add perforations to Well La-105. We perforated the sands above the Upper Logbaba D Sand, which has been our main producing reservoir in La-105 since start-up. In total, 57 metres of additional perforations were shot. After shooting the perforations, a production log was run in Well La‑105 to determine the contributions of the new zones to flow and a baseline for future logs. The newly perforated zones are performing well and will significantly contribute to production in the future as the lower sands deplete.
The Company is also making plans for the drilling of future wells at Logbaba that are aimed at increasing reserves and production to meet the growing gas demand in Cameroon.
In operations, VOG will make a number of key decisions over the next six months concerning where best to allocate gas supply. With strong increased demand rates expected in the first half of 2015, through the ENEO deal, the Board is now looking at the most effective ways to increase both margin and consumption within GDC.