Quarterly Report
Highlights from the December quarter include:
✓ Pre-construction update at Hemerdon Project, subsequent to quarter end
o Capital and operating costs updated
o Tungsten price forecast to strengthen
o Project is 'construction-ready' - construction to begin in February.
✓ Class A Mining Environmental Waste Permit granted for Hemerdon Project.
✓ Completion of property acquisitions required for development of project.
✓ Russell Clark appointed Managing Director.
✓Nick Clarke appointed to board as Non-executive Director, subsequent to quarter end.
NOTE:
A Metric Tonne Unit (mtu) is equal to ten kilograms and is the standard weight measure of the tungsten trade.
Pre-construction update provided for Hemerdon Tungsten-Tin Project
Subsequent to the quarter (ASX announcement, 20 January 2014) the Company provided a pre-construction update covering recent and planned activities at its world class Hemerdon tungsten and tin project in Devon, in the southwest of England.
Highlights of this update are provided below;
Project Milestones
· In May 2011, Wolf announced results of its Definitive Feasibility Study (DFS) for the Hemerdon Project and has now advanced the project to being 'construction-ready', with the following key milestones achieved in recent months:
o A US$75 million Bridge Finance Facility secured from major shareholder, Resource Capital Funds, to commence design and construction work;
o Senior Project Finance Facilities of £75 million from ING, Unicredit and CAT Financial established;
o £75 million fixed price, fixed term EPC contract awarded to GR Engineering Services (ASX: GNG) for the design and construction of the process plant;
o £85 million Mining Services contract awarded to CA Blackwell Ltd to mine the open pit and build the mine waste facility;
o All major permits to proceed with development have been received, and all properties required to be acquired as a condition of the project's Planning Permission have been purchased.
Project Timetable
· The Project remains on schedule to commence earthworks next month with construction scheduled to commence during Q2 2014.
Capital Costs
· Since announcing the positive results of the DFS, detailed design for the project has been undertaken and capital costs have been updated to reflect this work and to account for any variance in costs in the period of time since the initial costs were estimated in the DFS.
· The updated capital cost of the project is £123.2 million of which £106.7 million remained as at 1 December 2013.
Operating Costs
· As previously reported, the Company has appointed a mining contractor, an EPC contractor and has also recruited a local management team. With these key components now in place, the Project's operating costs have also been updated from those reported in the DFS to reflect current costings.
· The updated average C1 cash cost for the operation is US$109 per mtu tungsten (mtu = metric tonne unit = 10kg) net of by-products.
Financing
· The US$75 million Bridge Finance Facility is due to repaid by 7 June 2014 and first draw-down of the £75 million Senior Project Finance Facilities is subject to completion of conditions precedent (many of which have been satisfied) customary for a financing of this nature, including repayment of the Bridge Finance Facility.
· Wolf is now finalising the arrangements to complete project funding in parallel with project site activities.
Tungsten Market
· The Tungsten market has strengthened since the release of the DFS in 2011, with the current price range of US$370 - 390 per mtu. As announced on 20 January 2014, the Company commissioned an independent review of forecast tungsten prices with the following results:
more..