MoneyAM MoneyAM
 Home   Log In   Register   Our Services   My Account   Contact   Help 
 Stockwatch   Level 2   Portfolio   Charts   Research   Share Price   Awards   Indices   Market Scan   Company Zone   Traders' Room 
 Funds   Trades   Terminal   Alerts   Heatmaps   News   Stock Screener   Forward Diary   Forex Prices   Director Deals   Investors' Room 
 CFDs   Shares   SIPPs   ISAs   Forex   ETFs   Videos   Comparison Tables   Spread Betting   Broker Notes   Shares Magazine 
You are NOT currently logged in

 
Filter Criteria  
Epic: Keywords: 
From: Time:  (hh:mm) RNS:  MonAM: 
To: Time:  (hh:mm)
Please Note - Streaming News is only available to subscribers to the Active Level and above
 


Serica's North Eigg well hit by six-week delay and £3 million cost

ALN

Serica Energy PLC on Wednesday said its drilling operations on the North Eigg exploration well in the North Sea has encountered delays, which will cost the company £3 million.

Shares in the London-based oil & gas company were down 5.1% to 369.20 pence each in London on Wednesday morning.

Serica said that drilling operations on the North Eigg exploration well have encountered delays and, following a recent equipment failure, operations are now expected to take six weeks longer to complete than the original schedule.

The company explained that during the third section of the well there was a failure of a vital piece of rig equipment during routine pre-job testing. A replacement has now been found, it noted, and planning is underway to transport this to the drilling rig.

Serica said the delays will have no geographical impact on the well and that all costs will benefit from the investment allowances available under the recently introduced Energy Profits Levy.

However, the company expects the net well cost after tax to be around £3 million, as a result of delays and it now anticipates that results from the well will be available in December.

Chief Executive Mitch Flegg said: ‘This high-impact exploration well is the latest in a series of capital investment projects undertaken by Serica with the objective of increasing our production in an environmentally sensitive manner. This programme is designed to help increase the UK's security of supply and reduce its reliance on imports.’

‘The technical delays encountered on this project are extremely frustrating but do not impact either the chance of success or the significant prospective volumes of this exploration prospect,’ Flegg added.