MoneyAM MoneyAM
 Home   Log In   Register   Our Services   My Account   Contact   Help 
 Stockwatch   Level 2   Portfolio   Charts   Research   Share Price   Awards   Indices   Market Scan   Company Zone   Traders' Room 
 Funds   Trades   Terminal   Alerts   Heatmaps   News   Stock Screener   Forward Diary   Forex Prices   Director Deals   Investors' Room 
 CFDs   Shares   SIPPs   ISAs   Forex   ETFs   Videos   Comparison Tables   Spread Betting   Broker Notes   Shares Magazine 
You are NOT currently logged in

 
Filter Criteria  
Epic: Keywords: 
From: Time:  (hh:mm) RNS:  MonAM: 
To: Time:  (hh:mm)
Please Note - Streaming News is only available to subscribers to the Active Level and above
 


Metals Exploration’s Nicaragua gold project reaches 40% completion

ALN

Metals Exploration PLC on Monday said construction and development activities at the La India gold project in Nicaragua are continuing to advance ahead of schedule.

The project is now 40% complete, ahead of the 35% planned completion at mid-March, the company said.

The London-based minerals exploration firm, with assets in the Philippines as well as its Nicaragua development, expects first gold production at La India in December, in line with previous estimates.

The project budget increased by 3.6% to $171 million from $165 million, as total project expenditure to the end of February reached approximately $80 million, 2.6% higher than the $78 million originally forecasted.

The project is funded by free cash flow from the company’s Runruno gold mine in the Philippines, and a $30 million gold pre-pay facility.

However, the company is pursuing an equipment loan of $20 million to secure against its mining fleet, for which expenditures have reached $15 million out of a total projected cost of $29 million.

Metals Exploration said bulk earthworks are fully complete, while overall engineering is 85% complete. Further work is still required on the processing plant foundations, although 94,800 tonnes of low-grade commissioning ore have been stockpiled on the run-of-mine pad ahead of commissioning.

Overall, non-process infrastructure at the La India site is 77% complete.

Metals Exploration shares were up 1.9% to 12.53 pence each on Monday morning in London.